Single sided#

  1. Prepare two holes in a wall by hinges pitch on backside of the clock.

  2. Insert dowels to prepared holes and screw appropriate screws into them.

  3. Remove four screws on bottom of the clock. Remove the bottom cover and plexiglass.

    ../../_images/eco-m-dc_step3.svg
  4. Except PoE variant, use power cable of at least 3 x 0.5 mm² (double isolation), maximal 3 x 1.5 mm² (double isolation).

  5. Thread cable(s) through grommet and hang the clock on prepared screws in the wall.

    ../../_images/eco-m-dc_step5.svg
  6. Cut cable(s) to appropriate length and connect the wires to corresponding terminals or crimp the RJ45 jack to Ethernet cable respectively.

    Attention

    If the clock is synchronized by LGC variant, please navigate to Clock Operation Non-Network Clock Operation to get detailed info about connection of various synchronization sources and receivers.

    For LGC variant, check and configure the position of DIP switch according to used synchronization signal (applies only for DCF, MOBALine, polarized impulse line or IRIG‑B).

  7. Mount the plexiglass and bottom cover.